Repair pipe

20 workers had to repair broken pipes in 30 days. After fourteen days, four laborers joined them. How long did the pipe repair work last?

Correct answer:

x =  27.3333 d

Step-by-step explanation:


20•30 = 20•14 + (20+4)•(x-14)

24x = 656

x = 82/3 ≈ 27.333333

Our simple equation calculator calculates it.



We will be pleased if You send us any improvements to this math problem. Thank you!



avatar




Tips to related online calculators
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?

You need to know the following knowledge to solve this word math problem:

Related math problems and questions:

  • Road repair
    workers_1 Road repair took 10 days for 36 workers if they worked 9 hours a day. How many days take repair same road 37 workers if they work 8 per day?
  • Six workers
    workers Six workers planned to repair the roof in 5 days. After two days, two workers get sick. How long will the remaining workers complete the roof at the same rate of work?
  • 2 pipes
    time_12 2 pipes can fill a tank in 35 minutes. The larger pipe alone can fill the tank in 24 minutes less time than the smaller pipe. How long does each pipie take to fill the tank alone?
  • Two workers
    Frog Two workers together execute some work in 10 days. The first worker would have done himself in 20 days. How many days would have done himself a second worker?
  • Forestry workers
    forestry_workers In the forest is employed 56 laborers planting trees in nurseries. For 8 hour work day would end job in 37 days. After 16 days, 9 laborers go forth? How many days are needed to complete planting trees in nurseries by others if they work 10 hours a day?
  • Two pipes
    roura_1 How long will the pool be filled with a double supply pipe if it takes the pool to fill the first pipe by 4 hours longer and the second pipe 9 hours longer than both pipes open at the same time?
  • Work at plant
    workers_4 Handyman has vowed to do repair work at the plant for 25 days. However, work had to be shortened and therefore gained helper. Together they made all the corrections for 13 1/3 days. How long the work would take helper himself?
  • Three workers
    three_workers Three workers A, B, C have to work on a specific task. Workers A and B completed whole task in 14 days, B together with C for 23 days, A together with C for 13 days. How long it would take to complete the task every one of them alone? How long it would ta
  • Two pipes
    2pipes One pipe fill one-fifth volume 20 minutes before by second one. The two pipes together will fill the tank in two hours. How long is will fill tank each pipe separately?
  • Repairman
    makak Repairman has vowed to do repair work at the plant for 25 days. However work had to be shortened, and therefore he took helper worker. Together they made all the corrections for the whole days. How long it would take work to helper worker?
  • Digging companies
    companies Company A would dig a pit for 12 days, company B for 15 days, company C for 20 days and the company D for 24 days. Work began together companies C and D, but after three days joined them other two companies. How long took to dig a pit?
  • Workers
    zamkova_dlazba Ten workers must pave road street for 22 working days. After four days were for speeding up work added two more workers. a) After how many work days now workers completes the paved road? b) How many working days it took a total paved road?
  • Mukls
    Chinese women workers The working group, in which 6 workers would ordered job completed within 21 working days. How many workers must be accept yet that the contract will be completed in 14 working days?
  • Workers
    two_workers Two workers A and B, will be done work together for 15 days. They worked together for 13.5 days. Then A worker became ill, and worker B finish the job alone for 7.5 days. If every worker was working alone, how many days took whole work for worker A and B?
  • Inlet minus outlet
    inlets_6 Water flows into the tank through two pipes and flows out of the third pipe spontaneously. Pipe A itself would fill the tank in 3 hours, pipe B itself would fill in 4 hours, and pipe C would flow out in 12 hours. How long will the tank be full if all thre
  • Bricklayers
    murar Seven bricklayers will build the house in 630 days. How many bricklayers do we need to take after 150 days to complete the building for (additional) 336 days?
  • Workers
    work_9 9 workers dig a canal 120 meters long for eight hours. For how long would be dig five workers canal 200 meters long?