20 men

20 men are supposed to complete a work in 10 days. After working for 5 days, they realize that only one-fourth of the work is done. How many more men they need to employ to complete the work on time?

Final Answer:

x =  10

Step-by-step explanation:

w=20 10=200 w1=5 20=100 w2=41 w=41 200=41 200=4200=50  w3=ww2=20050=150  w3 = (x+20) (105)  w3/(105) = x+20  x=w3/(105)20=150/(105)20=10



Help us improve! If you spot a mistake, please let let us know. Thank you!