Workhorses
A team of colleagues did the work in 20 days. After adding two colleagues from the beginning, the team completed the work in 15 days. How many members has the colleague team?
Final Answer:

Tips for related online calculators
Do you have a linear equation or system of equations and are looking for a solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
algebraUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Installation team
The team of installers is to carry out the installation in 20 days. By adding two fitters from the beginning of the work, the assembly was completed in 15 days. How many were on the team? - Construction work
A group of masons had to finish the rough construction within three days. On the first day, they completed a third of this task, but on the second day, they were delayed and did 15% less work than the first day. By what % relative to the second day must t - Sick colleague
All the classrooms at school were painted during the holidays. On the first day, 6 painters did one sixth of the required work. From the second day until the painting was finished, only 5 painters worked because one of them got sick. All the painters work - Forest cleanup
A group of nature conservationists (a total of 28 members) and a sports team (16 members) worked for 7 days to clean up the forest park with an area of 10 ha. How many days would conservationists have to work without the help of athletes? - A contractor 2
A contractor has to complete his contract in 92 days. 234 men were set to do the work, each of them works for 16 hours/day. After 66 days, 4/7 of the work is completed. How many additional men may be employed, so that the work may be completed in time, ea - Workshop order days
In the first workshop, there are 3 workers; in the second workshop, 2 work equally efficiently. They worked on the order together, and for the last 2 days, only workers from the first workshop. If only the first workshop were working, the order would be c - Painters
The first team of painters would paint the bridge in 15 days, the second in 10 days. After three days of working together, the second team goes out and continues only with the first team. How many days took the second team to finish painting the bridge?