Installation team
The team of installers is to carry out the installation in 20 days. By adding two fitters from the beginning of the work, the assembly was completed in 15 days. How many were on the team?
Final Answer:

Tips for related online calculators
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
algebraUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Workhorses
A team of colleagues did the work in 20 days. After adding two colleagues from the beginning, the team completed the work in 15 days. How many members has the colleague team? - Three Groups Work Shifts
A group of fitters installed the cable line in 9 changes, and the second group completed the same task in 1/3 less time. How many shifts would the third group do the same work if, with all three groups working together, the assembly took 2 shifts? - Painters
The first team of painters would paint the bridge in 15 days, the second in 10 days. After three days of working together, the second team goes out and continues only with the first team. How many days took the second team to finish painting the bridge? - Construction work
A group of masons had to finish the rough construction within three days. On the first day, they completed a third of this task, but on the second day, they were delayed and did 15% less work than the first day. By what % relative to the second day must t - Toothpaste usage time
The father would use the toothpaste alone for 15 days, the mother for 12 days, and the daughter for ten days. It was used by all three for three days, then only the father and mother. How many days have they used it since the beginning of its use? - Assembly sick worker
Two assemblers with the same daily output were to complete the assembly in 12 days. After 4 days, one of them got sick, and the other finished the assembly in another 16 days. How long would it take everyone to do the assembly by themselves? - The track 2
The track team is trying to reduce their time for a relay race. First, they reduce their time by 2.1 minutes. Then, they are able to reduce that time by 1/10. If their final time is 3.96 minutes, what was their beginning time? Show or explain your reasoni