Eight diggers will do the job in 85 hours. After 21 hours, 3 diggers had to leave. How many hours will the work be done?

Correct answer:

t =  123.4 h

Step-by-step explanation:


8•85 = 21•8 + (t-21)•(8-3)

5t = 617

t = 617/5 = 123.4

Our simple equation calculator calculates it.



We will be pleased if You send us any improvements to this math problem. Thank you!






avatar




Tips to related online calculators
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Most natural application of trigonometry and trigonometric functions is a calculation of the triangles. Common and less common calculations of different types of triangles offers our triangle calculator. Word trigonometry comes from Greek and literally means triangle calculation.

Related math problems and questions:

  • Working time
    work_1 At 10 hours work shift, work is done in 16 days. How many days will the work be done at 8 hours shifts?
  • Contract
    clocks_5 8 employees complete the contract for 65 hours. After 17 hours, 3 employees had to leave for another job. How many more hours will the job on contract be fulfilled?
  • The work
    clock-night-schr_17 The work was to be done by 150 workers. At the beginning of their work, their number reduced by 40, which increased the time of work by 5 and 1/3 of the schedule. How long did work take?
  • The tank
    pipe2_4 The tank had 9 inflows to be filled in 21 days. After 9 days, 3 trips out. How many days did the remaining 6 tributaries fill the tank?
  • Two workers
    work One worker needs 40 hours to do a job, and the second would do it in 30 hours. They worked together for several hours, then the second was recalled, and the first completed the job itself in 5 hours. How many hours did they work together, and how much did
  • Five tractors
    tractors Five tractors plow the fields in 4.8 hours. How long will it take to plow the field when, after an hour and a half of work, two tractor drivers have been called up for another task?
  • Welders
    svarec Welder do the job for six hours, the second one for 8 hours. How long do the job third welder if all together can do job in 2 hours?
  • Painting rooms
    palma_1 If Dano paints three hours daily, he complete in 7.5 days. How many hours a day would have to work to finish the job 1.5 days earlier?
  • Three pumps together
    pumps One pump fills the tank in 1.5 hours, the second in 2 hours, and the third in 3 hours 20 minutes. How many minutes will the tank fill with three pumps if they work simultaneously?
  • Four workers
    wood_6 Four workers lay on the gym floor in six hours. After an hour of working together, one of the workers went to the doctor. How long will it take for the remaining three workers to complete their work?
  • Drying apples
    apples_3 By drying, apples lose 85% of their weight. How many kgs of dried apples do we get from 820 kilograms of fresh?
  • Painters 4
    painter_3 One painter will do the job for 12 days. After a 4 1/3 day he comes second to help him and complete work together for 8 days. How long would work the second painter himself?
  • Wood harvesting
    woord_2 The harvested wood is bundled from the forest to a sawmill. The driver makes the journey four times a day, and the work takes him 8 days. How many times would he have to go daily to get the job done 2 days earlier?
  • The field
    tractors 3 tractors plow the field in 6 hours. However, after 2 hours, 1 tractor broke down. How long will the field be plowed?
  • Blueberries
    blueberry 5 children collect 4 liters of blueberries in 1.5 hours. a) How many minutes do 3 children take 2 liters of blueberries? b) How many liters of blueberries will be taken by 8 children in 3 hours?
  • Mukls
    Chinese women workers The working group, in which 6 workers would ordered job completed within 21 working days. How many workers must be accept yet that the contract will be completed in 14 working days?
  • Work at plant
    workers_4 Handyman has vowed to do repair work at the plant for 25 days. However, work had to be shortened and therefore gained helper. Together they made all the corrections for 13 1/3 days. How long the work would take helper himself?