Road repair

Road repair took 10 days for 36 workers if they worked 9 hours a day.

How many days take repair same road 37 workers if they work 8 per day?

Correct answer:

x =  10.9 d

Step-by-step explanation:

x=36109378=10.9 d



Did you find an error or inaccuracy? Feel free to write us. Thank you!



avatar







Tips to related online calculators
Need help to calculate sum, simplify or multiply fractions? Try our fraction calculator.
Check out our ratio calculator.
Do you want to convert time units like minutes to seconds?

Related math problems and questions:

  • Forestry workers
    forestry_workers In the forest is employed 56 laborers planting trees in nurseries. For 8 hour work day would end job in 37 days. After 16 days, 9 laborers go forth? How many days are needed to complete planting trees in nurseries by others if they work 10 hours a day?
  • Workers
    zamkova_dlazba Ten workers must pave road street for 22 working days. After four days were for speeding up work added two more workers. a) After how many work days now workers completes the paved road? b) How many working days it took a total paved road?
  • Shoemaker
    shoes Both the shoemaker and his apprentice repaired his shoes. The apprentice worked for 6 days and repaired 10 pairs of shoes every day. The shoemaker did the same job in 4 days. How many pairs of shoes did the shoemaker repair per day?
  • Workers
    two_workers Two workers A and B, will be done work together for 15 days. They worked together for 13.5 days. Then A worker became ill, and worker B finish the job alone for 7.5 days. If every worker was working alone, how many days took whole work for worker A and B?
  • Working together
    workers Two people will do the work in 12 days. They worked together for 8 days. Then only one worked for 10 days. How many days would each of them do the work if he worked alone?
  • Working time
    work At 10 hours work shift, work is done in 16 days. How many days will the work be done at 8 hours shifts?
  • Six workers
    workers Six workers earned a total of CZK 12,600 per week on the construction site (5 working days). How much do 7 workers earn in 10 days with the same daily average salary?
  • Repair pipe
    workers 20 workers had to repair broken pipes in 30 days. After fourteen days, four laborers joined them. How long did the pipe repair work last?
  • Diggers
    workers The excavation was carried out in 4 days and 5 workers worked on it for 7 hours a day. Determine how long it would take to excavate if 7 workers worked on it 8 hours a day.
  • Painting school
    painting Redecoration school had scheduled for four crew to 10 days. After two days a single worker ill. For how many days the school was painted when remain workers working with the same tempo?
  • Reading records
    clock-night-schr Lucy, Tereza, and Petra decided to compile the compulsory reading records together. It would take 30 days for Lucia alone, 36 for Tereza and 45 for Petra. How long will it take to make records if they will work together?
  • Greenhouses
    sklenik Two workers would make installation of greenhouses for 54 hours. For how many hours does the installation have nine workers?
  • Tmp workers
    profesiadays Three temporary workers cleaned 60 m of walkway in 5 hours. How many meters of the walkway cleared seven volunteers for eight hours?
  • Excavation
    vykop_ryha Mr. Billy calculated that excavation for a water connection digs for 12 days. His friend would take 10 days. Billy worked 3 days alone. Then his friend came to help and started on the other end. On what day since the beginning of the excavation they met?
  • Digging
    digging The first worker would dig a trench in 6 hours. For the second, the same work would take 4 hours. How long did it take for the trench to be dug if they worked together?
  • Six workers
    workers Six workers planned to repair the roof in 5 days. After two days, two workers get sick. How long will the remaining workers complete the roof at the same rate of work?
  • Seven workers
    wood Seven workers clear the glade in 22 hours. How many workers would need to be done in 8 hours?