Tractors

Six tractors plowing the field for 8 days. After two days, two tractors broke down. How many days were prolonged work in the field?

Correct result:

x =  3 d

Solution:


6•8 = 2•6+(x+(8-2))•(6-2)

4x = 12

x = 3

Our simple equation calculator calculates it.



We would be pleased if you find an error in the word problem or inaccuracies and send it to us. Thank you!



Showing 0 comments:
avatar




Tips to related online calculators
Do you have a linear equation or system of equations and looking for its solution? Or do you have quadratic equation?
Do you want to convert time units like minutes to seconds?
Most natural application of trigonometry and trigonometric functions is a calculation of the triangles. Common and less common calculations of different types of triangles offers our triangle calculator. Word trigonometry comes from Greek and literally means triangle calculation.

Related math problems and questions:

  • Tractors
    tractor 6 tractors started plowing the field that them together take 12 days. Agronomist hesitates to A) after 2 days to withdraw 2 tractors, or B) after 3 days to withdraw 3 tractors. Help him which of these two cases will be plowing done sooner.
  • Tractors
    tractors_2 5 tractors will plow the field for 8 hours. In 2 hours, 1 tractor broke down. How long do the remaining tractors complete the plow?
  • The field
    tractors 3 tractors plow the field in 6 hours. However, after 2 hours, 1 tractor broke down. How long will the field be plowed?
  • Five tractors
    tractors Five tractors plow the fields in 4.8 hours. How long will it take to plow the field when, after an hour and a half of work, two tractor drivers have been called up for another task?
  • Five tractors
    tractor_1 Five tractors plow field in 4.8 hours. How long plow this field if after 1.5 hours of work two tractors went to a different field?
  • The orchard
    jablone 4 temporary workers harvested the orchard in 9 days. How many temporary workers we need for six days?
  • Lumberjacks
    stromy_17 Fifteen lumberjacks would take 12 days to destroy the broken trees. How many days would this work require if 5 workers added to it after 4 days?
  • Seven tractors
    koleso Seven tractor plowed 308 ha field in four days. How many hectares of fields will plowe 9 tractors in 3 days at the same power?
  • Painters
    time Ten painters paint the school in 20 days. How many days do four painters paint the school at the same pace of work?
  • Hectares of forest
    stromy 12 workers plant 24 ha of forest in 6 days. In how many days will 15 people and 12 people plant the same area?
  • Working time
    work_1 At 10 hours work shift, work is done in 16 days. How many days will the work be done at 8 hours shifts?
  • Water inlets
    pipe Inlet valve with a flow rate of 12 liters per second is filled tank for 72 minutes. How long take to fill full tank if we open one more such valve half an hour after?
  • Painters
    natieraci Five painters painting the fence for eight days. How many days over will take work if paint the fence only four decorators?
  • Six workers
    workers Six workers earned a total of CZK 12,600 per week on the construction site (5 working days). How much do 7 workers earn in 10 days with the same daily average salary?
  • Workhorses
    work A team of colleagues done the work in 20 days. After adding 2 colleagues from the beginning the work was completed in 15 days. How many members has the colleague team?
  • Painting rooms
    palma_1 If Dano paint three hours daily given work he complete in 7.5 days. How many hours a day would have to work to finish the job 1.5 days earlier?
  • Two workers
    workers_2 Two workers carry will do certain work for 12 days. After 8 days of working was one removed, and then the other finished the job alone in 10 days. For how many days would do this work alone each worker?