How many tons of cement are needed to concrete two pillars 6.5 m high with a base in the shape of four squares joined into one cross of dimensions 1.2 m? 2.5 q of cement is needed for 1 cubic meter of concrete.

Correct answer:

m =  18.72 t

Step-by-step explanation:

n=2 4=8 h=6.5 m a=1.2 m m1=2.5 q t=2.5:10  t=0.25 t  S1=n a2=8 1.22=25288=11.52 m2 V=S1 h=11.52 6.5=251872=74.88 m3  m=V m1=74.88 0.25=18.72 t