Order fulfillment

This company can complete the order in 168 days. The second company is better equipped and can fulfill the order in 120 days. The companies will fulfill the orders together. Determine how long it will take them to fulfill the order and in what proportion they will participate in its fulfillment.

Final Answer:

t =  70 d
r =  5:7

Step-by-step explanation:

t=1/(1/168+1/120)=70 d
r=1/(168/120)=750.7143=5:7