Two workers
Two workers together execute some work in 10 days. The first worker would have done it alone in 20 days. How many days would he have done it alone a second worker?
Final Answer:

Tips for related online calculators
Need help calculating sum, simplifying, or multiplying fractions? Try our fraction calculator.
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you have a linear equation or system of equations and are looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
algebrabasic operations and conceptsnumbersUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Workers
Two workers would fulfill a certain task when working together for 10 days, the first if he worked himself done work in 17 days. How many days will the second worker do the whole job? - Two Workers Work Days
Two workers would do the work together in 2 days. The first would do some work here in 6 days. In how many days would the second worker do this work? - Workers
Two workers, A and B, will be done work together for 10 days. They worked together for 8 days. Then A worker became ill, and worker B finished the job alone for 6 days. If every worker worked alone, how many days did the whole work take for workers A and - Two workers
Two workers work together and perform the job in 12 hours. If one has done half the work and then the second worker does the next half of the work, it will take 25 hours. How long would it take to job them separately? - Parquet floor
Three workers laid the parquet floor for 2.301 hour. The first would do this work alone 7 hours, the second in 6 hours. For how many hours would this work for the third worker if he worked alone? - Workers 2
The worker dug the trench for 7 hours, and another worker for 10 hours. They recruited to work even one worker. Digging should be done for 2 hours. For how long would dig the third worker alone? - Two workers
Two workers should fulfill specific tasks together for five days. If the first worker increased their performance twice and the second twice fell, it took them just four days. For how many days would he handle the entire task, the first worker himself?