Two workers would do the work together in 2 days. The first would do some work here in 6 days. In how many days would the second worker do this work?
Correct answer:
Tips for related online calculators
Do you have a linear equation or system of equations and looking for its solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
Units of physical quantities:
Themes, topics:
Grade of the word problem:
Related math problems and questions:
- Two workers
Two workers together execute some work in 10 days. The first worker would have done it himself in 20 days. How many days would they have done himself a second worker? - Workers
Two workers would fulfill a certain task when working together for 5 days, the first if he worked himself done work in 13 days. How many days will the second worker do the whole job? - Complete 5584
The two workers dug together for 6 hours. The first worker would do the work himself in 14 hours. How long would it take for the second worker to complete the task? - Parquet floor
Three workers laid the parquet floor for 2.301 hour. The first would do this work alone 7 hours, the second in 6 hours. For how many hours would fulfill this work for the third worker if he worked alone? - Two workers
One worker needs 40 hours to do a job, and the second would do it in 30 hours. They worked together for several hours, then the company recalled the second, and the first completed the job in 5 hours. How many hours did they work together, and how much di - Two workers
Two workers will do certain work for 12 days. After eight days of working, one was removed, and the other finished the job alone in 10 days. For how many days would you do this work alone for each worker? - Weighted harmonic average
Ten workers will do some work in 2 minutes, five in 10 minutes, and three in 6 minutes. How many minutes per average worker per worker? - Two workers
Two workers should fulfill specific tasks together for five days. If the first worker increased their performance twice and the second twice fell, it took them just four days. For how many days would he handle the entire task, the first worker himself? - Two companies
The two companies did work together for 100 days. The first company would do it in 150 days. How many days would the work take the second company? - Apprentice 20753
The trained worker will do the work in 4 hours. The apprentice needs 6 hours for the same work. How many hours and minutes would they do this work if they worked together? - Complete 23811
We ordered two parties of workers to replace the windows and doors. The first group would complete the task in 15 days. The second in ten days. How many days will they be able to exchange it together? - Repairman
The repairman has vowed to do repair work at the plant for 25 days. However, work had to be shortened, so he took a helper worker. Together they made all the corrections for the whole day. How long would it take work to help workers? - Insulation
Two workers insulate the house for five days. After the first day of working together, only one worker continue to cover the house. How many days will the house be insulated if every worker has the same work tempo? - Adjusting 72554
Two working groups are adjusting the park. The first group would do the work in 15 days, and the second in 25 days. How many days will they do the work together? - Two workers
Two workers work together and perform the job in 12 hours. If one has done half the work and then the second worker next half of the work, it will take 25 hours. How long would it take to job them separately? - Working together
One worker performs work in 3 days, the second in 5 days. How much do they work together? - Digging
The first worker would dig a trench in 6 hours. For the second, the same work would take 4 hours. How long did it take for the trench to be dug if they worked together?