Ten workers will perform the assigned work in 8 days. How long will it take to get the job done if six workers work for six days, and then another six join them?

Correct answer:

t =  9.6667 d

Step-by-step explanation:

m=10 8=80 md   m = 6 6 + (6+6) (t6)  t=6+2 6m6 6=6+2 6806 6=329 d=9.6667 d