10 workers
Ten workers will perform the assigned work in 8 days. If six workers work for six days and then another six join them, how long will it take to get the job done?
Final Answer:

Tips for related online calculators
Do you have a linear equation or system of equations and are looking for a solution? Or do you have a quadratic equation?
Do you want to convert time units like minutes to seconds?
Do you want to convert time units like minutes to seconds?
You need to know the following knowledge to solve this word math problem:
algebraUnits of physical quantitiesthemes, topicsGrade of the word problem
Related math problems and questions:
- Two workers
Two workers work together and perform the job in 12 hours. If one has done half the work and then the second worker does the next half of the work, it will take 25 hours. How long would it take to job them separately? - Workers
Two workers would fulfill a certain task when working together for 10 days, the first if he worked himself done work in 17 days. How many days will the second worker do the whole job? - Workers
Two workers, A and B, will be done work together for 10 days. They worked together for 8 days. Then A worker became ill, and worker B finished the job alone for 6 days. If every worker worked alone, how many days did the whole work take for workers A and - Additional Workers Needed
Certain work was to be done by 21 workers during an eight-hour workday, due in 12 days. After five days, temporary workers came to their aid. They all worked together for 7 hours a day and finished the job in 6 days. How many part-timers were there? - Workers 2
The worker dug the trench for 7 hours, and another worker for 10 hours. They recruited to work even one worker. Digging should be done for 2 hours. For how long would dig the third worker alone? - Sapling planting calculation
In the forest, there are 84 workers employed in planting saplings. Working 10 hours a day, they would finish the job in 24 days. After 7 days, 14 workers leave. How long will it take the others to finish planting the saplings if they work 12 hours a day f - Insulating a house
Five workers are insulating a house at a pace that would allow them to finish the job in 18 days. After three days of work, two workers were called away to another construction site. In how many more days will the remaining workers finish the job?