A construction 2

A construction company will be penalized for its bridge construction delays. The penalty is set at 4,000 for the first day and shall be subjected to a 1,000 increase for each succeeding day. The company can afford a maximum payment of 165,000 for a penalty. Find the maximum number of days by which the completion of work can be delayed.

Final Answer:

n =  15

Step-by-step explanation:

a1=4000 d=1000 b=165000  a2=a1+d=4000+1000=5000 a3=a2+d=5000+1000=6000  s(n) = 2n [ a1 + a1+(n  1)d ]  165000=n2 (2 a1+(n1) d)  165000=n2 (2 4000+(n1) 1000) 500n23500n+165000=0 500n2+3500n165000=0 500=2253 3500=22537 165000=2335411 GCD(500,3500,165000)=2253=500  n2+7n330=0  a=1;b=7;c=330 D=b24ac=7241(330)=1369 D>0  n1,2=2ab±D=27±1369 n1,2=27±37 n1,2=3.5±18.5 n1=15 n2=22  n=n1=15

Our quadratic equation calculator calculates it.




Help us improve! If you spot a mistake, please let let us know. Thank you!







Tips for related online calculators
Are you looking for help with calculating roots of a quadratic equation?
Need help calculating a sum, simplifying, or multiplying fractions? Try our fraction calculator.
Do you have a linear equation or system of equations and are looking for a solution? Or do you have a quadratic equation?

You need to know the following knowledge to solve this word math problem:

algebraarithmeticnumbersUnits of physical quantitiesGrade of the word problem

Related math problems and questions: