In a factory, four workers are assigned to complete an order received for dispatching 1400 boxes of a particular commodity. Worker A takes 4 minutes per box, Worker B takes 6 minutes per box, C takes 10 minutes per box, and D takes 15 minutes per box. Fin - The tank
The tank had nine inflows to be filled in 21 days. After nine days, three inflows shut down. How many days did the remaining six tributaries fill the tank? - Repair pipe
Twenty workers had to repair broken pipes in 30 days. After fourteen days, four laborers joined them. How long did the pipe repair work last? - Paul earned
Paul earned 300 CZK in one hour, Václav 1/3 more than Paul. Václav worked 60 hours, which is 1/3 fewer hours than Paul worked. How many percent less earned Paul an hour than Václav? How many hours did Paul more than Václav? How much did Paul earn more tha
- Our house
Our house would paint by four painters in 14 days. How long could it paint five painters? How long will it take if two other painters come to help after five days? - Together
If eight men, ten women, and 16 children collect ₹1024 in 4 days, how many days will be required for six men, five women, and four boys to collect ₹768? (₹ is Indian Rupee) - Distribute 6298
Sixteen employees will distribute leaflets in 12 days. How long will it take if, after four breaths, six workers go to work elsewhere? - Line-producing 6197
The new line-producing screws did not work at total capacity from the beginning. On Monday, she produced 20% of the daily norm. On Tuesday, she already met 4/5 of the daily norm. By what percentage was the number of screws made on Tuesday higher than on M - Wood harvesting
The harvested wood is bundled from the forest to a sawmill. The driver makes the journey four times a day, and the work takes him eight days. How often would he have to go daily to finish the job two days earlier?
- Together 5931
The tank will be filled with the first inlet in 5 hours and the second in 12 hours. How long would it take to fill the tank together? - Turners
Two turners perform joint work in 3 hours. The first-turner would perform the job himself in 7 hours. How long would the same job last for a second-turner if he worked alone? - Sick
Six seamstresses should make 60 shirts in five business days. After three days, two seamstresses were sick. How many days have the remaining seamstresses to finish the contract? - Three workshops
2743 people are working in three workshops. In the second workshop works, 140 people more than in the first and in the third works 4.2 times more than the second one. How many people work in each workshop? - In and out
The empty tank is filled in 12 minutes and empty in 16 minutes. How long does it take to fill if we forget to close the drain? The tank has 1000 liters of volume.
- Tractors
Two tractors plow the field for 4 hours together. If the first tractor plowed half of the field and then the second tractor completed the job, it would take 9 hours. How many hours does the field plow for each tractor separately? - Work
The first worker would need less than 4 hours to complete the task than the other worker. In fact, both workers worked for two hours together. Then the first worker did the remaining work himself. In what proportion should the remuneration of the workers - Highway tunnel
The company built the highway tunnel from two ends in the north-south direction. The average daily performance of the "northern party" rasters was higher than the average daily power of the "southern party" rasters. After 55 business days, both parties me - Two workers
Two workers should fulfill specific tasks together for five days. If the first worker increased their performance twice and the second twice fell, it took them just four days. For how many days would he handle the entire task, the first worker himself? - Calculate 5619
Jana had to calculate 70 tasks, and if she had solved two more daily tasks than she had planned, she would have finished four days earlier. How many days did she have to calculate the tasks?